Cases

ALPHA LISTING | CASE LAW 1999 | CASE LAW 2000 | CASE LAW 2001 | CASE LAW 2002 | CASE LAW 2003

CASE LAW -

Statute of Limitations to Enforce CC&Rs Commences When Demand for Performance Is Made. Cutujian v. Benedict Hills Estates Association (1996) 41 Cal.App.4th 1379, 49 Cal.Rptr.2d 166 [originally in Guralnick & Gilliland's Eleventh Annual Legislative Update]

CASE FACTS

In 1988, Eric K. Cutujian purchased a partially improved residential lot in a common interest development subdivision governed by the Benedict Hills Estates Association. Between 1976 and 1978, a surface slump occurred on the fill slope of the partially improved lot. Under the Association's CC&Rs, the Association had an affirmative duty to maintain, in a neat and safe condition, the natural and manmade slopes and corresponding drainage ditches on both the common areas and on the residential lots. This duty included the "repair and replacement of landscaping and improvements when necessary and appropriate."

In April 1988, prior to the close of his escrow on the lot, Cutujian demanded that the Association repair the damage to the slope so that he could subsequently commence building his residence. The Association did not refuse to repair the slope. However, subsequent to discussions regarding the costs and feasibility of repairing the slump, Cutujian determined that the Association was not going to effectuate repairs. Therefore, he repaired the surface slump at his own cost and brought action against the Association to recover the costs of repairing the surface slump on the property.

In his lawsuit, originally filed in 1989 and subsequently amended a first, second and third time, Cutujian alleged breach of covenant, negligence and, finally, continuing nuisance. In 1993, the Association moved for summary judgment, alleging that Cutujian's action was barred by the four year statute of limitations for actions on a written instrument (the CC&Rs). The Superior Court sustained the Association's motion on the basis that Cutujian did not timely file his action and, thus, exceeded the statute of limitations. Judgments for dismissal and attorneys' fees were entered in March 1994 in favor of the Association as the prevailing party in the action.

Cutujian filed an appeal on several points, the most applicable point being that his claim for damages was timely filed. The appellate court found in favor of Cutujian, reversed the lower court's decision, and sent the case back to the lower court for further deliberation.

ANALYSIS

The major issue before the court was not which statute of limitations applied to this case (3 years or 4 years, depending on the cause of action cited by Cutujian), but, rather, at what point in time did the statute of limitations begin to run. Unfortunately, the court found no California statute or judicial decision directly addressing when the statute commences for either an action to enforce CC&Rs or action to enforce a covenant running with the land which requires the performance of an affirmative act, i.e., the duty of the Association to repair the damaged lot. Therefore, the court relied heavily on a few rulings in similar cases reviewed by the Montana Supreme Court.

The court found the most reasonable ruling to be that the statute of limitations to enforce affirmative covenants running with the land, and, in particular, duties included in a declaration of CC&Rs, commence when a demand for performance is made. In reviewing the specifics of the Cutujian case, the court concluded that the express language contained within the CC&Rs, referencing the Association's responsibility to maintain the slope areas and to repair and replace improvements when "necessary and appropriate", clearly supported the Association's obligation to do so after Cutujian made his demand.

Furthermore, Cutujian was not barred from his action simply because the slump occurred 10 to 12 years prior to his purchase of the lot. On the contrary, the Association's duty to repair and maintain always existed as a covenant running with the land. However, the repair was not "necessary and appropriate" until such time when someone seriously contemplated building on the lot. Accordingly, Cutujian's purchase of the lot in 1988 and desire to build upon the lot triggered the "necessary and appropriate" repairs. The Association's failure to facilitate the necessary slope repairs was a violation of the CC&Rs.

The court disagreed with the Association's argument that any action was time-barred since damage to the slope occurred between 1976 and 1978. The court concluded that the statute of limitations began to run in 1988 when Cutujian demanded the Association repair the surface slump on his property. It found that the statute of limitations for an action such as Cutujian's was four years and commenced with the written demand to the Association.

As a side note, the court also determined that even if the statute of limitations did commence between 1976 and 1978, and did run by 1982, the end result would have been unjust to Cutujian because during that time the board was a developer-controlled board. Additionally, one of the developers was the predecessor-in-interest to the lot purchased by Cutujian. The predecessor had knowledge of the slump and the need to repair it, but never took action. The court stated it would have been unfair if Cutujian was estopped from pursuing his rights under the CC&Rs simply because of his predecessor's inaction.

CONCLUSION

The fact that Benedict Hills Estates Association's CC&Rs were recorded in 1976 and the fact that the damage to the slope occurred some time between 1976 and 1978 were not determining factors as to when the statute of limitations began to run. Rather, the determining factors were when Cutujian made his demand to the Association for performance under the CC&Rs and when he filed his suit to enforce same. Cutujian made his demand in 1988 and filed suit in the same year. Thus, his filing was timely.

*Important Note. This case stands for the proposition that where an association has an affirmative duty to repair, created by the CC&Rs, that duty may be a continuing requirement and the applicable statute of limitations may only begin to run with the homeowner's demand for the association to repair the property condition at issue. In other words, associations may be held responsible for rectifying property conditions which are more than four years old and a lawsuit may be filed based upon a written demand by the owner to the association within the four-year time period from that demand.

 

The information provided in this web page is offered for informational purposes only; it is not offered as and does not constitute legal advice. [Attorney/law firm] does not seek to represent you based upon your visit or review of this web page site.

Copyright © 2003 Guralnick & Gilliland, LLP Attorneys At Law, All Rights Reserved